NOTICE BOARD
Sebenza substation commissioning, Region E and F:
City Power's newest and biggest substation will be undergoing commissioning (equipment testing and preparation for switch-on) to bring the second transformer on board in the coming few weeks and this will entail power interruptions.
The areas that will be affected during the commissioning are as follows:
City Power's newest and biggest substation will be undergoing commissioning (equipment testing and preparation for switch-on) to bring the second transformer on board in the coming few weeks and this will entail power interruptions.
The areas that will be affected during the commissioning are as follows:
Alexandra
Athol Bagleyston Bellevue Birdhaven Birnam Bramley Bruma Chrislehurston Cristal Gardens Dewetshof Fairmount* Glenhove Glenhurst Highlands North Houghton Illovo Inanda Kent Park Kew Killarney Linksfield* |
Lombardy East
|
* Denotes Ward 72
Most of the work will be done at night to minimize power interruptions to business and other customers during this time. Sebenza substation is good news that comes after the first transformer at the substation was used to alleviate power shortages experienced in June.
Kelvin Power Station incapacity will no longer cripple the North Eastern suburbs of Johannesburg once the commissioning process is done. City Power appreciates the patience and understanding from the affected customers during this time of capacity augmentation.
During this time, there will be minor power interruptions. The good news is that Delta and Prospect substations will be backed up and supported by the increased capacity from Sebenza once the commissioning is completed.
City Power urges residents to bear with the utility during this time as this exercise is meant to increase supply capacity to ensure that unplanned power interruptions do not occur in the future without proper replacement capacity.
The substation has three transformers and are expected to be fully connected to the grid by end of November 2018.
Kelvin Power Station incapacity will no longer cripple the North Eastern suburbs of Johannesburg once the commissioning process is done. City Power appreciates the patience and understanding from the affected customers during this time of capacity augmentation.
During this time, there will be minor power interruptions. The good news is that Delta and Prospect substations will be backed up and supported by the increased capacity from Sebenza once the commissioning is completed.
City Power urges residents to bear with the utility during this time as this exercise is meant to increase supply capacity to ensure that unplanned power interruptions do not occur in the future without proper replacement capacity.
The substation has three transformers and are expected to be fully connected to the grid by end of November 2018.
Please always log your complaint using the City Power App to ensure that they attend to your issue.
CLICK HERE TO LOG COMPLAINT
CLICK HERE TO LOG COMPLAINT
Official notification from City Power
If any residents power has not been restored, please log your fault with City Power.